Almost every Rock Hill homeowner planning new construction, an addition, or a major remodel asks the same question: how long will the drywall actually take? Short answer for a typical 2,000 sq ft single-family home: about five working days on site, plus two to three days of mud cure between coats. The honest answer requires walking through the phases because work calendar and wall calendar are not the same thing.

Day 1: Material delivery and load-in

Drywall is delivered the day before or morning of hang day. A 2,000 sq ft home takes 90 to 120 sheets of half-inch board plus 10 to 20 sheets of specialty board (mold-resistant in wet areas, fire-rated for garage walls). Sheets unload through the largest available opening and lean against walls in every room based on the cut plan.

Days 2–3: Hang

Hanging is the fast phase. A two-person crew installs 90 to 120 sheets per day. Ceilings first, then walls, screwed every 12 inches on ceilings and 16 inches on walls. A 2,000 sq ft home is fully hung in one to two days; 3,500+ sq ft extends to three.

Days 4–6: First and second mud coats

First coat embeds paper or mesh tape over every seam and inside corner and covers every screw head. Inside corners and outside corner beads bed the same day. First coat dries overnight; second coat goes on the next morning and again dries overnight.

Day 7: Final coat and sanding

The third coat is the widest and thinnest, feathered to invisibility. Once it cures, the crew sands every joint and corner — one full day on a typical home. Then a wipe-down and vacuum and the home is ready for paint.

Common timeline complications

Vaulted ceilings or two-story foyers add scaffold setup. Custom finish (curved walls, archways, bullnose) adds finishing time. Level 5 adds one to two full skim-coat days plus dry time. Cold or rainy weather slows mud cure 24 to 48 hours.

Repair and remodel timelines

Small repairs: one-day visit with a return for touch-up. Single-room remodels (master bath, kitchen ceiling) take three to four working days across a week. Basement finishes are two to three weeks. Additions: one to two weeks for a bedroom or bath, two to three for a primary suite.

How we keep the schedule honest

Every quote includes a specific start date and finish date. When we tell you Friday, we mean sanded, vacuumed, walk-through complete, ready for paint. Call (803) 555-0400 or request a free quote — you get a calendar before we ever ask for a signature.